PMP cheat sheet 2026: formulas, domains, agile terms and exam-day facts on one page

By Angela Pedanyan · Updated:

This PMP cheat sheet condenses what is worth memorizing for the July 2026 exam into one page. It covers the exam-day numbers (180 questions, 170 scored, 240 minutes, two 10-minute breaks), the three domains weighted People 33%, Process 41% and Business Environment 26% with all 26 tasks, the eight question formats, the earned value, schedule, estimating and communication formulas with a worked example for each, the agile and hybrid vocabulary the exam uses, and the decision rules that resolve most situational questions.

Everything on this page is what is worth memorizing for the July 2026 PMP exam: the exam-day numbers, the three domains and their 26 tasks, the eight question formats, every formula that still appears, the agile and hybrid vocabulary, and the decision rules that resolve most situational questions. Print it, learn it, and spend the rest of your time on practice questions.

The exam facts and domain weights come from the official July 2026 PMP Examination Content Outline (PDF). The study method behind this sheet is in How to prepare for the PMP exam in 2026; what changed from the 2021 exam is in PMP exam changes July 2026.

1. Exam-day facts

FactValue
Questions180 (170 scored, 10 unscored pretest; you cannot tell which)
Time240 minutes
BreaksTwo, 10 minutes each: after the case-study section and midway through the independent questions
Pace80 seconds per question on average
Negative markingNone — answer everything
ResultProficiency level per domain (Above Target, Target, Below Target, Needs Improvement); no numeric score published
ReferenceJuly 2026 Exam Content Outline; PMBOK Guide, 8th edition listed as a reference
FormatComputer-based at a test center or online proctored

2. Domains, weights and the 26 tasks

DomainWeightTasks
I. People33%1 Develop a common vision · 2 Manage conflicts · 3 Lead the project team · 4 Engage stakeholders · 5 Align stakeholder expectations · 6 Manage stakeholder expectations · 7 Help ensure knowledge transfer · 8 Plan and manage communication
II. Process41%1 Develop an integrated project management plan and plan delivery · 2 Develop and manage project scope · 3 Help ensure value-based delivery · 4 Plan and manage resources · 5 Plan and manage procurement · 6 Plan and manage finance · 7 Plan and optimize quality of products/deliverables · 8 Plan and manage schedule · 9 Evaluate project status · 10 Manage project closure
III. Business Environment26%1 Define and establish project governance · 2 Plan and manage project compliance · 3 Manage and control changes · 4 Remove impediments and manage issues · 5 Plan and manage risk · 6 Continuous improvement · 7 Support organizational change · 8 Evaluate external business environment changes

Memory hook: 8 – 10 – 8. People and Business Environment have eight tasks each; Process has ten. Process is also the largest by weight, so it gets the most study time; Business Environment is the one most candidates under-prepare.

3. The eight question formats

FormatWhat you doTrap
Multiple-choice, single responsePick the one best answerTwo options are usually defensible; the exam wants the most proactive, collaborative one
Multiple-responsePick the stated number of correct optionsTreat each option as its own true/false; the stem says how many to select
MatchingPair items in two columnsLock in the certain pairs first, resolve the rest by elimination
Enhanced matchingMatching with more rows, categories or drag targetsSame technique; read the category labels before the items
Pull-down listComplete a statement from a dropdownRead the full sentence with each option inserted
Point-and-clickClick a region of an imageIdentify the artifact type first (burndown, Gantt, RACI, risk matrix)
Graphic-basedAnswer from a chart or diagramRead axes and legend before the question
Case scenarioSeveral linked questions on one multi-paragraph caseNote the delivery approach and project phase once, then answer each item against them

The exam opens with the case-study section, then moves to independent questions.

4. Earned value formulas

TermFormulaReads as
PVPlanned value: budgeted cost of work scheduled to dateWhat you planned to have done
EVEarned value: budgeted cost of work actually doneWhat you have done, in budget terms
ACActual cost of work doneWhat you spent
BACBudget at completionTotal planned budget
CVEV − ACPositive = under budget
SVEV − PVPositive = ahead of schedule
CPIEV ÷ ACAbove 1.0 = cost efficient
SPIEV ÷ PVAbove 1.0 = ahead of schedule
EAC (typical)BAC ÷ CPICurrent cost performance continues
EAC (atypical)AC + (BAC − EV)Past variances will not recur
EAC (both indices)AC + (BAC − EV) ÷ (CPI × SPI)Cost and schedule performance both continue
ETCEAC − ACWhat is left to spend
VACBAC − EACPositive = will finish under budget
TCPI (to BAC)(BAC − EV) ÷ (BAC − AC)Efficiency needed on remaining work to hit the budget
TCPI (to EAC)(BAC − EV) ÷ (EAC − AC)Efficiency needed to hit the revised estimate

Worked example. BAC = 100,000. By month 6 you planned to complete 50% of the work (PV = 50,000), you have completed 40% (EV = 40,000), and you have spent 45,000 (AC).

Reading rule: anything with EV on top and a comparison underneath (CPI, SPI) is an index — above 1.0 is good. Anything that subtracts (CV, SV, VAC) is a variance — positive is good.

5. Schedule and estimating formulas

ItemFormulaNote
Three-point (triangular)(O + M + P) ÷ 3Simple average of optimistic, most likely, pessimistic
Three-point (PERT / beta)(O + 4M + P) ÷ 6Weights the most likely estimate
Standard deviation (PERT)(P − O) ÷ 6One activity
Range at 1 sigmaPERT estimate ± SDAbout 68% confidence
Range at 2 sigmaPERT estimate ± 2 × SDAbout 95% confidence
Total floatLS − ES or LF − EFZero on the critical path
Free floatES (next activity) − EF (this activity)Delay without affecting the successor
Critical pathLongest path through the networkDetermines the shortest project duration
Communication channelsn × (n − 1) ÷ 2n = number of people, including the PM
Expected monetary valueProbability × ImpactSum across outcomes for a decision tree
Cost of qualityPrevention + Appraisal + Internal failure + External failureConformance vs non-conformance costs

Worked example (PERT). O = 4 days, M = 6 days, P = 14 days. PERT = (4 + 24 + 14) ÷ 6 = 7 days. SD = (14 − 4) ÷ 6 = 1.67 days. The 95% range is 7 ± 3.3, so 3.7 to 10.3 days.

Worked example (channels). A team grows from 6 to 9 people. Channels go from 6 × 5 ÷ 2 = 15 to 9 × 8 ÷ 2 = 36. Three people added, 21 channels added — which is why communication planning is a People task, not an afterthought.

Worked example (EMV). A risk has a 20% chance of costing 50,000. EMV = 0.2 × 50,000 = 10,000. A mitigation costing 8,000 that removes the risk is worth it; one costing 12,000 is not, on EMV alone.

6. Agile and hybrid vocabulary

TermOne-line meaning
Product backlogOrdered list of everything that might be built; owned by the product owner
Sprint / iterationFixed timebox (commonly 1–4 weeks) producing a potentially shippable increment
Sprint backlogItems selected for the current sprint plus the plan to deliver them
IncrementThe sum of completed backlog items at the end of a sprint
Definition of DoneShared checklist an item must satisfy to count as complete
VelocityStory points completed per sprint; used for forecasting, not for comparing teams
Burndown / burnupWork remaining / work completed over time
Daily standup15-minute sync: what was done, what is next, what is blocked
Sprint reviewDemonstrate the increment to stakeholders, gather feedback
RetrospectiveTeam inspects its own process and picks improvements
Product ownerOwns the backlog and value priorities
Scrum master / agile coachServant leader who removes impediments and protects the process
Servant leadershipLead by enabling the team: remove obstacles, coach, shield from interference
MVP / MBIMinimum viable product / minimum business increment — smallest release that delivers value
WIP limitCap on in-progress items (Kanban) to expose bottlenecks
Cycle time / lead timeTime from start to done / time from request to done
HybridPredictive and adaptive practices combined, e.g. predictive planning with iterative delivery
TailoringSelecting and adapting practices to the project, team and organization
Rolling wave planningPlan near-term work in detail, later work at a high level
Progressive elaborationRefining plans as more information becomes available

7. Predictive vocabulary that still appears

TermOne-line meaning
Project charterFormally authorizes the project and the PM; issued by the sponsor
Scope baselineScope statement + WBS + WBS dictionary, approved
Schedule baseline / cost baselineApproved schedule / approved time-phased budget
Change controlFormal process to review, approve or reject changes to baselines
Risk registerIdentified risks with analysis, owners and responses
Risk responses (threats)Avoid, mitigate, transfer, accept, escalate
Risk responses (opportunities)Exploit, enhance, share, accept, escalate
Contingency reserve vs management reserveFor known-unknowns, PM controls / for unknown-unknowns, management controls
RACIResponsible, Accountable, Consulted, Informed — one Accountable per task
Lessons learnedCaptured throughout, finalized at closure, stored in organizational process assets
Benefits realizationMeasuring whether the project delivered the business value it was approved for
GovernanceWho decides what, with which authority, under which escalation path

8. Decision rules for situational questions

These resolve most People and Business Environment items and many Process items.

When the question describes…The exam usually wants you to…Not to…
A conflict between team membersAddress it directly with those involved, understand the cause firstEscalate immediately, ignore it, or impose a solution
A team member underperformingTalk to them, find the obstacle, coach, adjust supportReplace them or report to their line manager first
A stakeholder unhappy with progressEngage them, understand the expectation gap, re-alignAvoid them or just send more reports
A change requestAssess impact, route through the change control process (or backlog in agile)Implement because the sponsor asked, or refuse outright
A new regulation or external changeAssess impact on scope, schedule, cost, risk; update the plan; inform stakeholdersWait and see
A risk that has materializedExecute the planned response; if none, treat as an issue and escalate per thresholdsCreate a new risk entry
An impediment blocking the teamRemove it yourself or escalate to whoever canTell the team to work around it
A sprint goal at riskDiscuss with the team and product owner; re-plan within the sprintExtend the sprint or add people mid-sprint
Closing a project or phaseObtain formal acceptance, release resources, archive, capture lessons, confirm benefitsStop when deliverables are handed over
Anything mentioning "first" or "next"Pick the step that gathers information or engages people before actingJump to the most decisive action

Three meta-rules: the project manager acts, not escalates, unless the question says it is outside their authority; collaboration beats command; the answer that follows the process beats the one that bypasses it, even when bypassing looks faster.

9. Numbers that show up in questions

NumberMeaning
1.0CPI/SPI threshold — above is good, below is bad
10 yearsWindow for the eligibility experience months (36 with a bachelor's degree, 48 with an associate's degree, 60 with a secondary diploma, 24 with a PMI GAC-accredited degree)
35Contact hours of project management education required to apply
60PDUs required every 3-year cycle to keep the credential
15 minutesDaily standup timebox
1–4 weeksTypical sprint length
3Points of a three-point estimate; sigma levels you may be asked about

10. How to use this sheet

  1. Week 1 of your plan: read it once, do not try to memorize it yet.
  2. Weeks 2–7: open it whenever a practice question uses a term or formula you hesitated on, and mark that row.
  3. Week 8: memorize the marked rows and the full formula tables.
  4. Mock exams: in the first two minutes, write the earned value and PERT formulas from memory on the scratch surface. If you cannot, you are not ready for that part of the exam.
  5. Exam day: do the same, then never look at it again — the rest of the exam is judgment, not recall.

The free PMP 2026 Study Console on this site tags every question to the domains and tasks above and scores you per domain, so you can see which rows of this sheet are costing you points.

Angela Pedanyan is an engineering manager who built the PMP 2026 Study Console while preparing for the exam. Exam facts and domain weights are from PMI's July 2026 Exam Content Outline; formulas follow standard PMI usage; decision rules are the author's reading of the ECO tasks, not PMI's.

Frequently asked questions

What formulas do I need to know for the PMP exam?

Earned value (CV, SV, CPI, SPI, EAC, ETC, VAC, TCPI), three-point and PERT estimates with standard deviation, communication channels n(n-1)/2, critical path and float, and expected monetary value. The 2026 exam has fewer pure calculation items than older versions, but these still appear, usually inside a scenario.

How many questions are on the 2026 PMP exam and how long is it?

180 questions, 170 of them scored, in 240 minutes with two 10-minute breaks: one after the opening case-study section and one midway through the independent questions.

What are the PMP exam domains and their weights in 2026?

People 33%, Process 41% and Business Environment 26%, covering 26 tasks in total. Business Environment grew from 8% in the 2021 outline to 26% in the July 2026 outline.

Is the PMBOK Guide 8th edition on the PMP exam?

The exam is written against the July 2026 Exam Content Outline, and PMI lists the PMBOK Guide, 8th edition, as a reference for it. Use the PMBOK for terminology and the ECO for what is actually tested.

Does the PMP exam penalize wrong answers?

No. There is no negative marking, so answer every question. Ten of the 180 items are unscored pretest questions, but you cannot tell which, so treat all 180 as scored.

Should I memorize a cheat sheet or understand the concepts?

Both, in that order of effort: memorize the formulas and the exam-day numbers because they are quick wins, then spend most of your time on situational practice, because the majority of the exam asks what a project manager should do, not what a term means.

Can I bring a cheat sheet into the PMP exam?

No. The exam is closed-book at test centers and online. Many candidates write the formulas from memory on the provided scratch surface in the first minutes of the exam; practice doing that in your mock exams.

What is the difference between CPI and SPI?

CPI = EV / AC measures cost efficiency: below 1.0 means you are spending more than planned for the work done. SPI = EV / PV measures schedule efficiency: below 1.0 means less work is done than planned by now.

Drill every formula and term in the free console